300-block and Capitol Quarter driveways work

Category: 
Update: 

Weather permitting, paving of the final asphalt surface between the sidewalk and alleyway for both Capitol Quarter driveway entrances is scheduled for next week:

  • On Monday (9/10), there will be milling and saw-cutting of the old pavement in both driveways to prepare them for final paving on the following days. There may be brief times when one or the other driveway is closed while workers and equipment are performing this work.
  • On Tuesday (9/11), the west driveway will be fully closed early in the morning to allow placement and rolling of the asphalt surface. It will remain closed to allow cooling/curing during the day, but will be re-opening the same evening. The east driveway will be open.
  • On Wednesday (9/12), the east driveway will be fully closed early in the morning to allow placement and rolling of the asphalt surface. It will remain closed to allow cooling/curing during the day, but will be re-opening the same evening. The west driveway will be open.

As mentioned before, this work is weather dependent and could shift a few days if we have bad weather.

There will be considerable workers and equipment working in the driveway entrances and the 300-block associated with this endeavor. The project team very much appreciates everyone’s patience as we work to get these important items completed.

Date: 
Friday, September 7, 2018