Work continues to progress on schedule on the street and open-space restoration at the intersection of 3rd Street and Virginia Avenue. Placement of new granite curbing and sidewalks, drainage work and underground preparations for streetlights are well underway.

During the week of Feb. 5th, driveway access for the Capitol Quarter townhomes will be switched from the temporary driveway on 3rd Street to the new permanent driveway from Virginia Avenue SE. Flaggers will be present to assist drivers in the area. CSX urges all drivers to use caution through this intersection. Pedestrian access will be maintained throughout this process. This work is dependent on favorable weather conditions and CSX will provide more information as the work progresses.

CSX appreciates the community’s patience as we work expeditiously toward completing the project and the streetscape enhancements. 