3rd Street Restoration Progress Continues

Category: 
Update: 

Work continues to progress on schedule on the street and open-space restoration at the intersection of 3rd Street and Virginia Avenue. Placement of new granite curbing and sidewalks, drainage work and underground preparations for streetlights are all well underway. Drivers are urged to be cautious as they navigate the new lane configurations on 3rd Street. As a clarification of the November Coffee with Chuck slides, CSX will not close 4th Street traffic until 3rd Street has been restored to 2-way, north-and-south bound traffic. Once traffic has reopened, there will still be some activities in the area to complete the brick sidewalks, granite curbs, plantings, and final streetscape installation. Additional schedule information will be distributed when it is available.

CSX appreciates the community’s patience as we work expeditiously toward completing the project and the streetscape enhancements.

Date: 
Thursday, December 14, 2017