CSX Team Completes Pile Drilling

Category: 
Update: 

The Clark/Parsons JV Virginia Avenue Tunnel team this week finished drilling the final street-level piling in support of excavation for the entire VAT project. Those pilings – 2,215 in all – form the framework for the walls that allow excavation for the two new tunnels. The team drilled over 24 miles of holes, and completed the effort right on schedule. The entire project remains on schedule for completion by mid-2018, within the 42-month construction period identified at the outset.   

Date: 
Friday, March 31, 2017