Cross-street Updates

Category: 
Update: 

Work continues on installation of the new temporary bridge deck at 5th/6th Street and is expected to be completed in mid- to late-March. The intersection will be re-opened immediately upon completion and inspection of the new structure.

Once the 5th/6th Street intersection is re-opened to vehicle traffic, the 7th Street intersection will be closed for installation of the Phase II bridge deck. That work is expected to take up to 4 weeks. Information about detours will be provided in advance of the 7th Street closing.

Work on installation of the Phase II bridge deck at 8th Street continues while the street remains open to traffic. Additional lane shifts will occur and drivers are encouraged to follow all directional signs and barriers. Work on the 8th Street bridge is expected to require up to 6 weeks to complete.

Pedestrian access will be maintained across all of these intersections while the new bridge decks are installed.

Date: 
Wednesday, February 22, 2017